Buyer's guide · Checked against the text of Republic Act 6552, October 2026

The Maceda Law (RA 6552): Your Protection as an Installment Buyer

Republic Act No. 6552, the Realty Installment Buyer Act, is the law most people call the Maceda Law. It protects anyone buying real estate on installments, and residential condominium units are expressly covered. If you miss payments, it gives you three things:

  • Time to catch up. A grace period, at least 60 days, or one month for every year you have paid.
  • Part of your money back. After two years of installments, 50% to 90% of everything you paid if the contract is cancelled.
  • A formal, 30-day cancellation. No contract ends until 30 days after a notarized notice reaches you.

This page describes the law in general terms and is not legal advice. The Act is short, and reading it in full takes about five minutes. For how it applies to your own contract, ask a Philippine lawyer.

What the law covers

The Act applies to sales and financing of real estate on installment payments, including residential condominium units. It does not cover industrial lots, commercial buildings, or sales to tenants under the agrarian reform laws.

Down payments, deposits and option money all count as installments when the law works out how long you have been paying.

The two-year line: grace period and refund

Your rights depend on whether you have paid at least two years of installments. The Act draws one line, and gives a different set of protections on each side of it.

Section 3 of the Act

At least two years of installments paid

  • A grace period without added interest. You earn one month of grace for every year of installments paid, and you may pay what is overdue within it without additional interest. You can use this right once in every five years of the contract, including any extensions.
  • A refund if the contract is cancelled. The seller must refund the cash surrender value: 50% of the total payments you have made. After five years of installments, it rises by five percent for every further year, up to 90% of total payments.
  • Cancellation takes time and money. A cancellation only takes effect 30 days after you receive a notice of cancellation or demand for rescission by notarial act, and only once the cash surrender value has been paid to you in full.
Section 4 of the Act

Less than two years of installments paid

  • A grace period of at least 60 days from the date the missed installment fell due.
  • Cancellation still needs notice. If it is still unpaid when the grace period ends, the seller may cancel the contract, but only 30 days after you receive a notice of cancellation or demand for rescission by notarial act.
  • No cash surrender value. Below two years, the Act provides no refund.

What happens after a missed installment

The Act sets the order of events. Nothing happens on the day a payment is missed, and nothing ends without a written notice and time to act.

  1. An installment is missed

    The clock starts on the date the installment fell due. Nothing happens on that day.

  2. The grace period

    At least 60 days with under two years paid; one month for every year paid once you pass two years, with no added interest. In this window you may also sell or assign your rights, or reinstate the contract.

  3. A notarized notice

    If it is still unpaid when the grace period ends, the seller sends a notice of cancellation or demand for rescission by notarial act.

  4. 30 days later

    Only then may the contract end. With two years paid, not before the cash surrender value has been paid to you in full.

How the refund is computed

The Maceda Law refund, which the Act calls the cash surrender value, is a share of the total payments you have made, down payment included. It starts at 50% once you pass the two-year line and climbs five percent a year after the fifth year.

Installments paidShareCash surrender value
Less than 2 yearsNone under the Act
2 to 5 years50%
6 years55%
7 years60%
Each further year5% more
Ceiling90%

An example. Suppose you have paid ₱1,000,000 in total over four years, counting the down payment, and the contract is cancelled. The cash surrender value is 50% of ₱1,000,000, which is ₱500,000. Had you paid for seven years, it would be 60%, or ₱600,000.

Your other rights under the Maceda Law

Four protections apply whether you are above or below the two-year line.

  • Sell or assign your rights. During the grace period and before actual cancellation, you may sell your rights under the contract or assign them to another person. The deed must be done by notarial act.
  • Reinstate the contract. During the same window, you may reinstate the contract by updating the account.
  • Pay ahead. At any time, you may pay any installment in advance, or the full unpaid balance, without interest, and have the full payment annotated on the certificate of title.
  • These rights cannot be signed away. Any contract clause made after the Act that goes against these rights is void.
The pool deck and gazebos at Kai Garden Residences, DMCI Homes condo in Mandaluyong, actual photo
What the installments are for: Kai Garden Residences, Mandaluyong, a completed DMCI Homes community. Actual photo.

Maceda Law questions, answered

A summary of the Act, one question at a time, each answered in its first sentence with the statute behind it.

What is the Maceda Law?

Republic Act No. 6552 of 1972, the Realty Installment Buyer Act. It gives buyers of real estate on installments, condo units included, a grace period when they miss payments and, after at least two years of payments, a refund of 50% to 90% of what they paid if the contract is cancelled.

How much is the Maceda Law refund?

50% of the total payments you have made, once you have paid at least two years of installments. After five years of installments it rises by five percent for every further year, to a ceiling of 90%. Below two years, the Act provides no refund. The Act calls this amount the cash surrender value.

How is the Maceda Law refund computed?

Take the total payments you have made, down payment included, and apply the percentage for the years paid: 50% for two to five years, then five percent more for each further year, up to 90%. On ₱1,000,000 paid over four years that is ₱500,000; over seven years, 60%, or ₱600,000.

How long is the Maceda Law grace period?

At least 60 days from the due date if you have paid less than two years of installments. With two years or more paid, one month for every year of installments paid, without added interest, usable once in every five years of the contract.

Does the Maceda Law apply to condo units?

Yes. The Act expressly covers residential condominium apartments, alongside other real estate sold on installments. It excludes industrial lots, commercial buildings and sales to tenants under the agrarian reform laws.

What if I have paid less than two years of installments?

You still get a grace period of at least 60 days from the date the installment fell due, and the contract can only be cancelled 30 days after you receive a notice of cancellation or demand for rescission by notarial act. The Act provides no cash surrender value below two years.

Do the down payment and reservation deposit count?

Yes. The Act counts down payments, deposits and option money as installments when working out how long you have been paying, and they form part of the total payments the refund is computed on.

Can I sell or assign my rights before the contract is cancelled?

Yes. During the grace period and before actual cancellation, the Act lets you sell your rights under the contract or assign them to another person, by notarial act, or reinstate the contract by updating the account. Buyers often call the sale of rights a pasalo.

How does a seller cancel under the Maceda Law?

Only by a notice of cancellation or demand for rescission by notarial act, and the cancellation takes effect 30 days after you receive it. With two years of installments paid, it also waits until the cash surrender value has been paid to you in full.

Can a contract waive Maceda Law rights?

No. The Act makes any contrary clause in a contract void.

The other side of the bargain: buildings delivered on time

The Act protects you if your side of an installment contract slips. The developer's side is the building itself, turned over on the date it committed to. DMCI Homes publishes those dates, and its record on them is a matter of public announcement, often a year early. Six examples, each with the committed date beside the actual one:

  • Brio Tower, DMCI Homes condo in Guadalupe, Makati, seen from the air at dusk
    Brio Tower, Makati13 months early
  • The towers of Lumiere Residences, DMCI Homes condo in Pasig, lit at night
    Lumiere Residences, Pasigtwo towers a year early
  • The three towers of Kai Garden Residences, DMCI Homes condo in Mandaluyong, from the air
    Kai Garden Residences, Mandaluyongon its launch dates
  • Alder Residences, DMCI Homes condo in Acacia Estates, Taguig, from a drone
    Alder Residences, Taguigall four buildings on schedule
  1. Brio Tower, MakatiTurnover began in late October 2018, 13 months ahead of its committed November 2019 schedule.
  2. Lumiere Residences, PasigThe East Tower was ready for turnover in September 2017 against a committed October 2018, and the West Tower in June 2018 against June 2019, each a year early. The North Tower followed in November 2020, the month committed when the project launched in 2015.
  3. Maple Place, Acacia Estates, TaguigLinden (January 2019) and Aspen (April 2019) each arrived 13 months ahead of their committed dates, and Spruce (September 2019) ten months ahead of the July 2020 date committed at its 2015 launch.
  4. Eleven buildings in 2020Through a year that included a 76-day construction stoppage under the lockdown, DMCI Homes completed four projects and turned over eleven buildings.
  5. Kai Garden Residences, MandaluyongSugi (January 2023), Icho (January 2024) and Hinoki (from June 2024) were turned over on the dates set out when the project launched.
  6. Alder Residences, TaguigLaunched in August 2020, in the middle of the pandemic, all four buildings arrived on schedule, from Andea in June 2024 to Sylvan on 1 December 2025.

Dates are as announced by DMCI Homes at the time and reported in the business press. A building is turned over by floor section over several months after the first move-ins, so the date for your own unit is the one in your turnover notice. Your DMCI Homes specialist can tell you a project's construction stage at any time.

Read the law, then ask a lawyer

The full text of Republic Act No. 6552 is nine sections long and is published by the Supreme Court E-Library and other public law libraries. This page summarizes it and gives no instructions for any particular situation. For your own contract, a Philippine lawyer is the right person to ask.

  1. Republic Act No. 6552, the Realty Installment Buyer Act (1972), full text
  2. DMCI Homes announcements: Brio Tower (October 2018); Lumiere Residences East, West and North towers (September 2017, June 2018, November 2020); Maple Place (27 June and October 2019); year-end 2020 completions (December 2020); Kai Garden Residences (19 March and July 2024); Alder Residences (3 December 2025)
  3. BusinessMirror, 29 November 2018: DMCI turns over Makati project ahead of schedule

Related reading: the DMCI Buyer's Guide, the rent to own DMCI condo program, and Pag-IBIG housing loans for DMCI condos.